Government
Through The Road Development Agency (Rda) Is In The Process Of Up Grading The
Kitwe-Chingola Road Into A Dual carriage Way At An Estimated Cost Of About 600
Billion Kwacha.
Rda
Acting Director And Chief Executive Officer Bernard Chiwala Said At A Press briefing
In Lusaka This Morning That An initial
Amount Of 100 Billion Kwacha Has Been Allocated For The 45.5kilometers Under The Annual Work Plan To Facilitate The commencement
Of Works Before The End Of the Year.
Mr.
Chiwala Says The Design For The Construction Of The Dual Carriageway Which stretches
From Kazembe Junction In Kitwe To Kasumpe Junction In Chingola Are already In
Place Following A Detailed Feasibility Study That Was Conducted By ranking
Engineering.
He
Says The Construction Of The Dual Carriageway Between Kitwe And Chingola Has been
Necessitated By Increased Traffic Volumes Travelling Between The Two Towns and
Beyond.
Mr.
Chiwala Has Pointed out That with Increased Mining Activities on the copperbelt
As well As the Democratic Republic of Congo, and the Establishment of New Mines
in Northwestern Province, Traffic on the Road has increased significantly Over
The Years.
He
Says Traffic Studies Conducted So Far Have Revealed That An Average Of2550-2600
Vehicles Per Day Travel In Each Direction Between Kitwe And Chingola and
22percent Of The Traffic Is Heavy Traffic.
Mr.
Chiwala Has Stated That The Road Whose Construction Period Is Within 2 And Half
Years Will Upon Completion See A
Reduction In The occurrence Of Road Traffic Accidents .
Meanwhile
To Improvement Transparency In the
Procurement Process Of The Project and Reduce Corruption, Mr. Chiwala
Says The Agency Has Written To The anti-Corruption Commission (Acc) Urging The
Investigating Agency To participate In
The Evaluation Process.